Service management deep-dive · Lesson

Change models

Quick answer

Normal, standard and emergency change, change models, risk assessment and the standard change template process.

Key takeaways

  • Change models make change types configurable, not coded
  • Standard changes are approved once as templates
  • Emergency change needs retrospective review to stay honest
  • A healthy standard change ratio shortens CAB

Change types

Normal change follows full assessment and CAB. Standard change is pre approved, low risk and repeatable. Emergency change is for restoring service and gets retrospective review. Getting the mix right is what makes CAB shorter.

Change models

A change model defines the states, transitions and approvals for a type of change. Models replaced hard coded workflow logic, so a new model is configuration rather than a workflow rewrite.

Standard change catalog

Standard changes come from templates that go through a proposal and approval cycle once.

  • Propose the template, review it, publish it, then anyone can raise that change without CAB
  • Review published templates periodically, retire the ones nobody uses
  • Measure the ratio of standard to normal change, rising standard change usually means the process is maturing

Want to learn this properly?

Our live, instructor-led ServiceNow Training covers this hands-on, with real projects and a certification path.

Check your understanding

  1. What defines the states and approvals for a change type?

    • A. A workflow only
    • B. A change model
    • C. A UI policy
    • D. An SLA
    Show answer

    B. A change model

    Change models hold the state flow and approval policy.

  2. A standard change template is approved

    • A. Every time it is used
    • B. Once, at publication
    • C. By the CAB weekly
    • D. Never
    Show answer

    B. Once, at publication

    Pre approval at publication is what removes CAB from routine work.

Frequently asked questions

Who approves a standard change?

Nobody at request time. The template was approved when it was published, which is the entire point.

How is risk calculated?

Through risk conditions or a risk assessment questionnaire. Both feed the risk field which drives approvals in the model.